Context
Site and water surveys began in 1938 and major construction followed in 1939. The two main plant sections were commissioned in stages during 1941 and 1942. A plant card dated 18 August 1941 records a site area of 3,364,000 m². The complex had its own wells, workshops, utilities, roads and internal railways.
Key findings
The page separates securely documented facts from reconstruction. Comparative data from other DSC plants is used only when explicitly labelled as analogy.
How to read the evidence
Direct Forst records take priority. Report 133 is direct evidence for corporate structure, while its detailed technical inventory concerns Kraiburg.
Open questions
Further archival finds may refine dates, quantities and machine identifications. Uncertain points remain visibly marked.